Objectives and purpose
ANESCO, one of the UK’s leading developers of battery energy storage projects, commissioned Smith Brothers to work on the delivery of the 20MW Lascar battery energy storage site, following a string of successful joint projects.
With a target energisation date of Spring 2019, and appointed as the Independent Connection Provider (ICP), Smith Brothers was tasked with constructing a 33kV metered connection supply substation to ENWL specification.
Works also included the installation of a 430 metre, 33kV cable connection to Kearsley grid supply point.