Lascar Battery Energy Storage Site

Electricity North West Ltd (ENWL) January – April 2019

Objectives and purpose

ANESCO, one of the UK’s leading developers of battery energy storage projects, commissioned Smith Brothers to work on the delivery of the 20MW Lascar battery energy storage site, following a string of successful joint projects.

With a target energisation date of Spring 2019, and appointed as the Independent Connection Provider (ICP), Smith Brothers was tasked with constructing a 33kV metered connection supply substation to ENWL specification.

Works also included the installation of a 430 metre, 33kV cable connection to Kearsley grid supply point.

n enwl3 railwaybridge lascar
NERSUVDBISO 9001ISO 14001ISO 45001ConstructionlineCHASUVDBRoSPASupply Chain Sustainability School
Download Brochure | Call Us